Donate to MHCD
MHCD Mental Health Center of Denver Enriching Lives and Minds
main

News for our Neighbors

Recovery Center Virtual Tour
Adult_Recovery_Center_Virtual_Tour

Click the image for a
virtual tour of the building

Mental Health Center of Denver Recovery Center Breaks Ground

Providing Economic and Environmental Benefits to Denver
More Information

Have a Question or Comment?

If you have a question or a comment about MHCD's new building please contact us!
We will be glad to answer your questions.

Frequently Asked Questions

Learn More About MHCD

About MHCD
MHCD Fast Facts sheet

Welcome to 4455 Building News!

Check back frequently to find out the latest progress on our building renovations.

MHCD purchased the property at 4455 E. 12th Ave. with a plan to consolidate four existing adult clinics into one location.

As CEO Dr. Carl Clark explains, “When MHCD committed to moving from an illness-management perspective to a recovery focus, it meant we needed to increase the number of people we were serving. Over the past five years, we doubled the number served but have not doubled the space available for outpatient services. That is why purchase of a new property became so important.”

Led by CFO Forrest Cason, board and staff leadership worked for many months to determine the best solution to our space problem. MHCD contracted with City Projects, a company whose motto is “Social Change through Real Estate”, to help us conduct a space study. Based on the study findings, we determined that the most efficient and effective plan would be to consolidate four of our adult clinics. We then began researching potential sites. When we found the property formerly known as the North Pavilion at 4455 E. 12th Ave., we knew we had found the right home for our adult recovery services. City Projects will remain our representative throughout the construction phase of the building.

Because MHCD is very strong operationally, we were able to purchase the property at the end of 2010 and move forward with planning for its complete renovation to make it a welcoming space for those we serve and for our exceptional staff members. A project design team has been meeting to guide the design and remodeling process. Davis Partnership has been selected at the project architect to design the remodeled space to make it into a landmark recovery facility that is also green and sustainable.

Taylor Kohrs was selected as the General Contractor and has been working on the demolition of the interior of the building so that construction can begin early Fall 2011.


MHCD Project Milestones

As with any major project like this, there are milestones along the way:

November 30 Demolition of the 1930-50's building will occur
Week of November 28 Parking garage construction is anticipated pending permit approval

Note:
There will be more activity at 4455 E. 12th Avenue with additional trucks and evacuation equipment. Our building contractor, Taylor Kohrs will continue to oversee the construction and the Mental Health Center of Denver is here to answer any of your questions or concerns.

July, 2012

Anticipated Opening of the 4455 East 12th Avenue Site

October 2011 Demolition is proceeding and is expected to be completed.
September 21, 2011 The Rezoning is moving through the City process. The Planning Commission meeting is Scheduled for September 21, 2011

July, 2011

Demolition and renovation begins

June 1, 2011

Taylor Kohrs has been selected as the General Contractor

June 6, 2011 

The Rezoning Application has been submitted to the city of Denver

June 16, 2011 

The Bellevue Hale Neighborhood Association and the Colorado Boulevard Health District have provided Letters of Support

June 17, 2011 

The final design for the exterior and interior renovation has been completed

June 30, 2011

The University of Colorado has vacated the property

Week of July 5, 2011

Renovation to the interior of the building will start 

July 27, 2011

Taylor Kohrs has developed a Construction Staging Plan that will be shared with the Bellevue Hale Neighborhood Association

February, 2011

MHCD initiates information meetings with Bellevue-Hale Neighborhood Association and Colorado Boulevard Health District

February, 2011

Architectural firm selected: Davis Partnership

February, 2011

Design process begins with completion anticipated by end of April, 2011

January, 2011

City Projects selected as MHCD’s Owner’s Representative

December, 2010

MHCD Board of Directors approved purchase of building from University of Colorado and financing plan with BBVA Compass Bank

November, 2010

Contract negotiations underway and financing secured

October, 2010

Property at 4455 E. 12th Avenue identified as possible option

August, 2010

City Projects leads effort for site selection

April, 2010

City Projects completes strategic assessment report identifying space needs and options

December, 2009

MHCD achieves our strategic goal of doubling the number of clients served

November, 2009

MHCD conducts strategic review of our financial position

January, 2005

Dr. Clark sets strategic vision for MHCD to double the number of consumers served

 


Press Releases

February 16, 2010 - Mental Health Center of Denver acquires building for future adult services recovery center